Work orders / WO-2026-01153
P2 WO-2026-01153
Corrective work order, Verified. At Convention Center Annex.
Response
- Priority
- P2, working-hours response (Mon–Fri 07:00–18:00 Pacific)
- Created
- Nov 13, 17:00 PST
- Response due
- Nov 18, 08:00 PST
- Planned
- Nov 16, 13:50 PST
- On site
- Nov 16, 14:00 PST
- Completed
- Nov 16, 16:10 PST
- Verified
- Nov 16, 17:40 PST
Who and where
- Site
- Convention Center Annex TW-SEA-003
- Technician
- Marcus Bennett, Seattle
- Contact
- +1-206-555-0201, marcus.bennett@example.com
- High voltage cert
- Yes, valid until Mar 31, 2027
- Charge points
- TW-SEA003-CP1
Notes
GroundFailure on TW-SEA003-CP1. Ground fault detected during pre-charge; sessions abort before power flows.
Faults answered
| Fault | Severity | Age | Charge point | Raised | Origin | Work order |
|---|---|---|---|---|---|---|
| FLT-26-0952
GroundFailure, Closed |
High | 7 d 21 h | – | Nov 13, 16:10 PST | ChargePoint | No work order |
Service visits
Nov 16, 14:00 PST to 16:10 PST
Marcus Bennett
- Findings
- Insulation resistance low on the output; the ground fault interrupter trips under load.
- Work done
- Reseated and secured the affected assembly, restarted the charge point; insulation test passed and three test sessions completed.
Parts fitted
No part fitted under this work order.