Sites / TW-SEA-011
Ballard Yards Charging
TW-SEA-011, Mixed use, Active. 5701 24th Ave NW, Seattle WA 98107
Open faults
In the fault listNo open fault at this site.
Open work orders
No open work order.
Site
- Parking bays
- 12
- Grid connection
- 300 kW
- Opened
- May 10, 2022
- Location
- 47.6702, -122.3876
- Host
- Ballard Yards Development yards@example.com
- Contract
- Apr 2022 to Apr 2027, 7% revenue share, $950 a month, 6 months notice
Charge points
| Charge point | Model | Status | Online | Last heartbeat | Connectors | Supplier | Warranty until |
|---|---|---|---|---|---|---|---|
| TW-SEA011-CP1 VG15-220316 |
VG-DC150 DC 150 kW |
InService | Online | Nov 10, 07:50 PST | 1 CCS1: Available 2 NACS: Available |
VoltGrid Systems Inc. | Apr 28, 2027 |